The project involved a two-storey (4th & 5th floor), penthouse apartment, located in the iconic, grade I listed, St. Pancras Chambers. The Northern, Piccadilly & Victoria Lines are below ground level, at this location.
The client wished to mitigate subsequent structureborne noise & vibration from underground train pass-bys, specifically, inside one of the bedrooms, to create a quiet space, isolated from the rest of the apartment, for work, rest & relaxation.
As a guide to how a change in sound level might be perceived subjectively, the table below sets out descriptions of subjective impression & commonly used adjectives, according to various bands of sound level change.
Band of Change in Sound Level (dB) | Subjective Impression | Descriptive Adjective |
---|---|---|
0 to 2 | Imperceivable change in loudness | Marginal |
3 to 4 | Perceivable change in loudness | Noticeable |
5 to 9 | Up to a doubling or halving of loudness | Significant |
10 to 15 | At least a doubling or halving of loudness | Substantial |
16 to 20 | Up to a quadrupling or quartering of loudness | Substantial |
21 or more | More than a quadrupling or quartering of loudness | Very Substantial |
The on-site feasibility survey is an opportunity for Mute Tube® to understand the building construction, assess the practicability of potential remedial works & help the client understand the implications of those works, before they commit to pre-works noise & vibration testing.
Pre-works noise & vibration testing is arguably the most critical process of all.
Here, Mute Tube® measures & maps the building's internal surfaces, responsible for propagating noise producing vibrations from passing underground trains & establishes the dominant frequency bands of those vibrations.
The building's dominant vibration pathways, established during pre-works testing, are the internal surfaces most in need of remedial treatment; these may be the floor, walls &/or ceiling.
The dominant frequency bands of those vibrations, informs the remedial system's requisite natural resonant frequency.
Mute Tube® develops the remedial system, as per the aforementioned assessment, often in collaboration with an architect &/or structural engineer.
Typically, installations form part of larger building contracts; as such, Mute Tube® works closely with the main contractor, to ensure supporting works facilitate a successful outcome.
Following installation, Mute Tube® conducts pre-completion noise & vibration testing, to gauge the efficacy of remedial works.
Typically, this is done once the building is ready for habitation, such that any residual noise & vibration levels measured, reflect what the end-user's acoustical experience will be.
Mute Tube® benchmarks pre-completion test data against Transport for London’s "Noise & Vibration Asset Design Guidance" & the World Health Organization’s general internal noise guidance for dwellings.
"Crossrail Information Paper D10", is also referenced, where appropriate.
The first step involved a feasibility survey, which is fundamental to every Mute Tube® project, for the following reasons:
To understand the building construction &, in turn, assess the practicability of potential remedial works.
To help the client understand the implications of potential remedial works, which is, typically, easier to do in-person.
The client was then able to make an informed decision, to progress to the next step: pre-works noise & vibration testing.
Pre-works noise & vibration testing is designed to establish the following, critical information:
The internal surfaces most notably propagating noise producing vibrations, from passing underground trains & the dominant frequency bands of those vibrations, i.e. the former informs the surfaces most in need of remedial attention & the latter informs the requisite natural resonant frequency of the remedial system.
The average LAeq,T (dB) & LAFmax (dB) noise levels, from passing underground trains, i.e. to benchmark against WHO & TfL guidelines, respectively, as a way of determining the requisite performance criterion for remedial works.
In this case, the 4th floor bedroom was the focus for remedial works. The floorplan below shows the elected noise & vibration test positions.
Test Position | Noise Source | LAeq (dB) Mean (Range) | LAFmax (dB) Mean (Range) |
---|---|---|---|
N1 | Train pass-bys (33 samples in 1 hr 09 mins) | 29 (27 - 30) | 33 (30 - 35) |
N1 | No train pass-bys | 27 | - |
Mean structureborne noise levels were measured at 29 dB, LAeq. As such, they satisfy the WHO's internal noise guidance for dwellings, which recommends that day & nighttime noise in bedrooms should not exceed 35 dB & 30 dB, LAeq, respectively.
In terms of noise, the levels measured at test position N1, averaged, from 33 train pass-bys, at 29 dB, LAeq & 33 dB, LAFmax. Notably, the former was 6 dB lower than the WHO’s daytime guidance for bedrooms, whilst the latter was 2 dB lower than TfL’s more stringent standards, set out in their "Noise & Vibration Asset Design Guidance".
In terms of vibration, from train pass-bys, the highest levels were measured at test positions Vb & Vf, in the horizontal ‘y’ axis (perpendicular to wall), from the plasterboard wall-linings, at 16.2 mm/s2 (max) & 13.4 mm/s2 (max), respectively. Notably, at the same test positions, from the supporting masonry wall (directly behind), i.e. Va & Ve, vibration levels, on the same 'y' axis, measured 2.23 mm/s2 (max) & 1.68 mm/s2 (max); demonstrating an 87% acceleration in vibration, caused by the plasterboard wall-linings.
As per the assessment of pre-works test data, the highest levels of noise producing vibration, from train pass-bys, were measured from the plasterboard wall-linings &, as such, it was decided these surfaces should be the focus for remedial works.
Because of the building's timber joist construction, the floor was not compatible with the requisite remedial system; both in terms of subsequent height & mass. Fortuitously, the mean vibration levels measured at position Vg (floor), in the vertical 'z' axis (where they were highest), were 40% less than those measured at positions Vb, Vd & Vf (walls), in the horizontal 'y' axis.
Following remedial works to the bedroom, pre-completion sound insulation tests were undertaken.
The floorplan below shows the elected noise and vibration test positions.
In terms of noise, levels were remeasured at test position N2, with an average, from 15 train pass-bys, of 28 dB, LAeq & 29 dB, LAFmax; a 1 dB & 4 dB reduction, respectively, on the levels measured pre-works.
Notably, regarding the average LAeq,T (dB) noise levels, this represents a 2 dB improvement on the World Health Organization’s nighttime guidance for bedrooms of 30 dB, LAeq. Concerning the LAFmax (dB) noise levels, these surpass, by 6 dB, Transport for London’s most stringent design target of 35 dB, LAFmax.
At the 50 - 63 Hz frequency range, where noise from passing trains peaked, pre-works, at 44 dB, Leq, there was a 6 dB reduction, whilst, across the dominant frequency bands (between 31.5 Hz & 200 Hz), post-works measurements showed a notably closer relationship between train pass-bys & typical background noise levels (see graph below). Generally, the extent to which the former exceeds the latter, is an indication of adverse impact.
In terms of vibration, from train pass-bys, levels were remeasured at test position Va (position Vd, pre-works), in the horizontal 'y' axis, at 4.48 mm/s2 (max), compared with 10.00 mm/s2, pre-works, which equates to a 55% reduction.
Test Position | Noise Source | LAeq (dB) Mean (Range) | LAFmax (dB) Mean (Range) |
---|---|---|---|
N2 | Train pass-bys (15 samples in 34 mins) | 28 (27 - 28) | 29 (28 - 32) |
N2 | No train pass-bys | 27 | - |
If Mute Tube® can be of assistance, then please do not hesitate to get in touch; we look forward to discussing your project with you.